Handed over to buyers.
Two towers framing the Opera District plaza, delivered on the announced quarter with retail and dining at podium level.
The AQARCHECK verdict
Promised Q3 2023, delivered Q3 2023 — on time.
Emaar Properties is Platinum tier, delivering 87% of tracked projects on time with an average slip of 1.4 months.
At AED 2,380/sqft, 16% below the Downtown Dubai average of AED 2,827/sqft across 3 tracked projects.
Launch pricing started at AED 1.8M. We do not yet track resale prices for this project, so no capital growth figure is shown.
Compiled from verified data. Not editable by developers or agents.
Delivery record
Promised at launch
Q3 2023
Delivered
Q3 2023
Delivered in the quarter promised at launch
Delivery is recorded to the quarter. We do not hold a handover date to the day for this project and have not estimated one.
Unit mix
- Size range across all types
- 700 sqft – 2,100 sqft
- Total units
- 660
Per-type size bands and starting prices are not published for this project. We show the range that covers all unit types rather than dividing it up, because that division would be a guess.
True cost to buy
The cheapest unit, with the costs that do not appear on a price list.
- Price, cheapest unitFrom the developer's price list
- AED 1,750,000
- DLD transfer fee4% of the purchase price
- AED 70,000
- Off-plan registrationFixed fee, payable on registration
- AED 3,000
- Admin feeFixed fee
- AED 580
Estimated. Fees are the published schedule and can change; mortgage, agency and valuation costs are not included.
What you actually get
Handover condition
Unfurnished
About Downtown Dubai
Emaar's flagship master community and the address most international buyers anchor on. Burj Khalifa, Dubai Mall and Dubai Opera sit inside a walkable core with the emirate's deepest short-let demand.
- Metro
- Burj Khalifa / Dubai Mall — 5 min walk
- Beach
- Jumeirah Beach — 12 min drive
- Airport
- DXB — 15 min drive
- Schools
- 6 within 15 min
Building detailsSpecification, counts and amenities
- Floors
- 52
- Swimming pools
- 2
- Parking spaces
- 720
- Elevators
- 8
- Retail units
- 14
- Ownership
- Freehold
- Handover condition
- Unfurnished
- Size range
- 700 sqft – 2,100 sqft
Wellness
Water
Lifestyle
Convenience
Gallery and documents
Documents
- BrochureNot disclosed
- Payment planNot disclosed
- Price listNot disclosed
The 42-point record
The same 42 points on every project, whatever its type or stage. We hold 27 of them here. The rest say so rather than disappearing — a record with gaps you can see is worth more than one that hides them.
70%
Complete
A · Identity
- 1Project name
- Act One | Act Two
- 2Developer
- Emaar Properties
- 3Emirate and community
- Dubai · Downtown Dubai
- 4Map pin
- Not disclosedRequest this
Every point in Location is computed from this.
- 5Property types
- Apartment
- 6Status
- Completed
B · Verification
- 7Registry project number
- RERA-P-18-0611DLD · verified 1 Aug 2026
- 8Advertising permit and expiry
- Not disclosedRequest this
The broker's advertising permit, not the developer's project registration.
- 9Escrow bank
- Emirates NBDDLD · verified 1 Aug 2026
- 10Escrow reference
- Not disclosedRequest this
We hold the last four digits only. Check the full number on your SPA against the developer's filing.
- 11Last verified
- 1 Aug 2026
C · Timeline
- 12Sales launch date
- Not disclosedRequest this
- 13Handover promised at launch
- Q3 2023
Held write-once: no ordinary edit can move it.
- 14Current handover target
- Q3 2023
- 15Construction progress, with its read date
- 100% · read 1 Aug 2026RERA · verified 1 Aug 2026
D · Size and units
- 16Total units
- 660
- 17Unit types offered
- 1 BR · 2 BR · 3 BR
- 18Size range per unit type
- 700 sqft – 2,100 sqft across all types
- 19Floor plan per unit type
- Not disclosedRequest this
- 20Parking per unit type
- Not disclosedRequest this
E · Price and payment
- 21Price from and to
- From AED 1,750,000
- 22Price per sqft
- AED 2,500 /sqft
Derived from the price and the smallest unit. In sqft, not m².
- 23Payment plan, four numbers
- 10 / 60 / 30
- 24Construction-linked or time-linked
- Not disclosedRequest this
A time-linked plan keeps taking money from a stalled site.
- 25Price last updated
- 1 Aug 2026
F · Running costs
- 26Service charge
- Not disclosedRequest this
- 27Cooling provider, and is chiller free
- Not disclosedRequest this
- 28Ownership type
- Freehold
G · Location
- 29Distance to five fixed places
- Not disclosedRequest this
Computed from the map pin. Distance is arithmetic; drive time needs a routing provider we do not yet have, and we will not publish one we cannot source.
- 30Nearest metro or tram, with walk time
- Not disclosedRequest this
- 31Master community
- Downtown Dubai
H · What you actually get
- 32Amenities
- 7 across 4 categories
- 33Handover condition
- Unfurnished
- 34What is NOT included
- Not disclosedRequest this
The single most trust-building thing on a property page, and almost nobody writes it.
I · Media and documents
- 35Hero photo and at least five more
- Not disclosedRequest this
- 36Brochure and payment plan
- Not disclosedRequest this
- 37Dated construction photos
- Not yet — construction has not started
J · Computed
- 38Delay against the original promise
- None — unchanged since launch
- 39Delivery health
- Delivered
This project has been handed over.
- 40Total cost to buy
- AED 1,823,580 — estimated
Estimated. Fees are the published schedule and can change; mortgage, agency and valuation costs are not included.
- 41Developer score
- 91.5 / 100
- 42Data completeness
- 70%
10 of the points that carry the completeness score are still open on this project. Every one of them is research we owe you rather than a fact the developer is withholding, and the request button beside each says which ones people are asking for.
Common questions
Answered from the verified data on this page, not from marketing material.
Was Act One | Act Two delivered on time?
Act One | Act Two was promised for Q3 2023 at launch and handed over in Q3 2023 — on time. AQARCHECK records delivery to the quarter.
Is the escrow account for Act One | Act Two verified?
Act One | Act Two has a registered escrow account with Emirates NBD under permit RERA-P-18-0611, last checked by AQARCHECK on 1 Aug 2026. Always confirm the account number on your SPA against the developer's official filing before transferring funds.
What did Act One | Act Two sell for at launch?
Launch pricing started at AED 1,750,000. Act One | Act Two is handed over, so units now trade on resale at prices set by sellers.
Who is the developer of Act One | Act Two?
Emaar Properties, rated Platinum tier by AQARCHECK with a score of 91.5 out of 100. Across the projects we track they deliver 87% on time, with an average slip of 1.4 months.
Resale cost calculator
This project is handed over, so buying here is a resale transaction. The costs below are the standard Dubai resale costs, not a developer payment plan.
- DLD transfer fee
- AED 74,200
- Agency commission
- AED 35,000
- Trustee office fee
- AED 4,200
- Total cash needed
- AED 1,863,400
4% of price plus AED 4,200 admin
2% is typical and is negotiable
AED 500K and above band
Purchase price plus all transaction costs
Transaction costs are the current standard DLD and trustee rates. Annual service charges are not included here — see the service charges section. Nothing on this page is a quote.
Regulatory status
- Project permit number
- RERA-P-18-0611
- Escrow bank
- Emirates NBD
Always confirm the escrow account number on your SPA against the developer's RERA filing before transferring funds.
Developer
- On-time rate
- 87%
- Average slip
- 1.4 months
Related projects
Other developments in Downtown Dubai and from Emaar Properties.
Grande Signature Residences
Opera District, Downtown Dubai, Dubai
Emaar Properties91.5From
AED 2.8M
Handover
Q2 2024
The Address Residences Dubai Opera
Opera District, Downtown Dubai, Dubai
Emaar Properties91.5From
AED 2.5M
Handover
Q4 2022