Design Quarter

Dubai Design District, Dubai

Under construction and selling from the developer.

Three towers inside d3 with canal frontage, aimed at the design and creative community that anchors the district.

Starting price

AED 2,300,000

Target handover

Q2 2027

Developer

Meraas

Total units

580

The AQARCHECK verdict

  • Escrow account verified with Mashreq, last checked 5 Aug 2026.

  • Handover has moved from Q4 2026 promised at launch to Q2 2027 — 6 months later.

  • Meraas is Gold tier, delivering 71% of tracked projects on time with an average slip of 3.8 months.

Compiled from verified data. Not editable by developers or agents.

Delivery record

Promised at launch

Q4 2026

Current target

Q2 2027

Moved back 6 months

This launch promise was recorded before we began storing the source alongside it, so we cannot yet name the announcement it was read from. The date itself is held write-once and has not moved.

Construction, as verified by AQARCHECK45%
RERA · verified 5 Aug 2026

We publish construction checkpoints only where we have verified the reading and can name its source. This project has one current reading and no earlier verified history — so none is shown rather than estimated.

Unit mix

1 BR2 BR3 BR
Size range across all types
760 sqft – 2,600 sqft
Total units
580

Per-type size bands and starting prices are not published for this project. We show the range that covers all unit types rather than dividing it up, because that division would be a guess.

True cost to buy

The cheapest unit, with the costs that do not appear on a price list.

Price, cheapest unitFrom the developer's price list
AED 2,300,000
DLD transfer fee4% of the purchase price
AED 92,000
Off-plan registrationFixed fee, payable on registration
AED 3,000
Admin feeFixed fee
AED 580
Estimated totalEstimatedAED 2,395,580

Estimated. Fees are the published schedule and can change; mortgage, agency and valuation costs are not included.

What you actually get

Handover condition

Unfurnished

About City Walk

Meraas' low-rise urban district off Al Wasl Road — European-style streets, retail at grade, and residential above. Walkable in a way most of Dubai is not.

Beach
Jumeirah — 6 min drive
Downtown
8 min drive
Retail
On site, 200+ units
Airport
DXB — 15 min drive
Explore City Walk
Building detailsSpecification, counts and amenities
Floors
31
Swimming pools
3
Parking spaces
720
Elevators
9
Retail units
14
Ownership
Freehold
Handover condition
Unfurnished
Size range
760 sqft – 2,600 sqft

Wellness

Gym

Water

Infinity pool

Lifestyle

Co-working spaceArt studioLandscaped podiumBoardwalk

Convenience

Covered parking24/7 security

Gallery and documents

Documents

  • BrochureNot disclosed
  • Payment planNot disclosed
  • Price listNot disclosed

The 42-point record

The same 42 points on every project, whatever its type or stage. We hold 27 of them here. The rest say so rather than disappearing — a record with gaps you can see is worth more than one that hides them.

70%

Complete

A · Identity

1Project name
Design Quarter
2Developer
Meraas
3Emirate and community
Dubai · City Walk
4Map pin
Not disclosedRequest this

Every point in Location is computed from this.

5Property types
Apartment
6Status
Under Construction

B · Verification

7Registry project number
RERA-P-23-2177DLD · verified 5 Aug 2026
8Advertising permit and expiry
Not disclosedRequest this

The broker's advertising permit, not the developer's project registration.

9Escrow bank
MashreqDLD · verified 5 Aug 2026
10Escrow reference
Not disclosedRequest this

We hold the last four digits only. Check the full number on your SPA against the developer's filing.

11Last verified
5 Aug 2026

C · Timeline

12Sales launch date
Not disclosedRequest this
13Handover promised at launch
Q4 2026

Held write-once: no ordinary edit can move it.

14Current handover target
Q2 2027
15Construction progress, with its read date
45% · read 5 Aug 2026RERA · verified 5 Aug 2026

D · Size and units

16Total units
580
17Unit types offered
1 BR · 2 BR · 3 BR
18Size range per unit type
760 sqft – 2,600 sqft across all types
19Floor plan per unit type
Not disclosedRequest this
20Parking per unit type
Not disclosedRequest this

E · Price and payment

21Price from and to
From AED 2,300,000
22Price per sqft
AED 3,026 /sqft

Derived from the price and the smallest unit. In sqft, not m².

23Payment plan, four numbers
20 / 40 / 40
24Construction-linked or time-linked
Not disclosedRequest this

A time-linked plan keeps taking money from a stalled site.

25Price last updated
5 Aug 2026

F · Running costs

26Service charge
Not disclosedRequest this
27Cooling provider, and is chiller free
Not disclosedRequest this
28Ownership type
Freehold

G · Location

29Distance to five fixed places
Not disclosedRequest this

Computed from the map pin. Distance is arithmetic; drive time needs a routing provider we do not yet have, and we will not publish one we cannot source.

30Nearest metro or tram, with walk time
Not disclosedRequest this
31Master community
City Walk

H · What you actually get

32Amenities
8 across 4 categories
33Handover condition
Unfurnished
34What is NOT included
Not disclosedRequest this

The single most trust-building thing on a property page, and almost nobody writes it.

I · Media and documents

35Hero photo and at least five more
Not disclosedRequest this
36Brochure and payment plan
Not disclosedRequest this
37Dated construction photos
Not disclosedRequest this

J · Computed

38Delay against the original promise
6 months later than promised
39Delivery health
Delayed

Handover has moved back 6 months since launch.

40Total cost to buy
AED 2,395,580 — estimated

Estimated. Fees are the published schedule and can change; mortgage, agency and valuation costs are not included.

41Developer score
82 / 100
42Data completeness
70%

10 of the points that carry the completeness score are still open on this project. Every one of them is research we owe you rather than a fact the developer is withholding, and the request button beside each says which ones people are asking for.

Common questions

Answered from the verified data on this page, not from marketing material.

When will Design Quarter be handed over?

The current target is Q2 2027. That is 6 months later than the Q4 2026 promised at launch. AQARCHECK last verified construction at 45% on 5 Aug 2026.

Is the escrow account for Design Quarter verified?

Design Quarter has a registered escrow account with Mashreq under permit RERA-P-23-2177, last checked by AQARCHECK on 5 Aug 2026. Always confirm the account number on your SPA against the developer's official filing before transferring funds.

What is the payment plan for Design Quarter?

A 60/40 plan: 20% on booking, 40% during construction, 40% on handover. A 4% Dubai Land Department transfer fee applies on top of the purchase price.

How much does Design Quarter cost?

Prices start at AED 2,300,000, around AED 2,490 per sqft, last checked 5 Aug 2026.

Who is the developer of Design Quarter?

Meraas, rated Gold tier by AQARCHECK with a score of 82 out of 100. Across the projects we track they deliver 71% on time, with an average slip of 3.8 months.

Payment plan

60/40
  • Down payment20%AED 460,000
  • During construction40%AED 920,000
  • On handover40%AED 920,000
  • Down paymentOn booking
  • During constructionAcross 8 milestones
  • On handoverAt completion

Payment calculator

Based on the 60/40 plan. Instalments are billed against construction milestones, not a monthly schedule.

Due at booking

20% down + AED 96,200 fees

AED 556,200
During construction

40% billed against construction milestones

AED 920,000
Due on handover

40% of the purchase price

AED 920,000
Total cash to handover

Full purchase price plus fees

AED 2,396,200

Indicative only. Milestone instalments fall due when construction stages complete, so their timing shifts with the build. Service charges, mortgage costs and agency fees are not included.

Regulatory status

Project permit number
RERA-P-23-2177
Escrow bank
Mashreq
DLD · verified 5 Aug 2026

Always confirm the escrow account number on your SPA against the developer's RERA filing before transferring funds.

Developer

82/ 100
Meraas

3 projects

Gold tier
On-time rate
71%
Average slip
3.8 months